POES Launch Update
2/03/09
- Countdown began this evening with spacecraft power on at approximately 2000
PST. Overnight the planned operations on
the spacecraft will be CPU loading, fight enable,
thruster enable and ordnance plug installations. Final spacecraft closeouts and fairing flight
door sealing are scheduled to begin around 0730 PST Tuesday and be completed by
1000 PST. Liftoff is scheduled for 02:22:01 am PST Wednesday morning.
The
weather forecast is favorable for the Wednesday morning launch attempt, but
degrades considerably for the rest of the week.
There is a Pacific storm headed this way. February 4th: T-0 Probability of
Violation: 20% due to Surface Winds. 24
Hour Scrub POV: 80% due to Surface
Winds, Thick Clouds, and Moderate Precipitation
For
countdown status call one of the following phone numbers:
|
NOAA-N Prime launch
hotline: |
301-352-4805 |
Laurie Kleppin will be updating |
|
KSC launch status
line: |
805-734-2693 |
George Diller from KSC
public affairs will be updating |
|
GSFC launch status: |
301-286-NEWS option 2 |
Cynthia O'Carroll from
GSFC public affairs will be updating |
If
you would like to monitor the countdown clock and events, go to the following
website for a live clock and video feed:
http://countdown.ksc.nasa.gov/elv/index-vafb.html
1/23/09 - On Friday the separation system ordnance connections were
completed. The firing harness was routed from the Delta II second stage
to the spacecraft payload attach fitting and subsequently mated to the clamp
band separation system initiators. Separation system catcher closeouts
will be completed on Saturday along with various mechanical and thermal flight
closeout activities in preparation for Fairing installation. Pre
encapsulation technical and management walk downs are scheduled for 12 hours
beginning at 1400 PST Monday and Fairing installation is scheduled to begin
early Tuesday morning.
1/21/09-1/22/09 – Early Wednesday the
crews performed link verification testing of the SBA,
1/20/09 - Spacecraft processing
resumed in the white room on Tuesday with deconfiguration
from Aliveness Testing and configuration for Link Checks. Activities
completed today included thermal blanket dressing, preload instrumentation wire
clipping, Omni antenna installations & mates, and NFI removals for flight. Power
up for antenna link checks is planned for Tuesday evening with the testing
taking the majority of night shift. Expect spacecraft power off by 0700
PST Wednesday.
1/17/09-1/19/09 –
1/16/09 - The contamination
shroud was removed from the spacecraft today and launch pad testing
configuration activities commenced. All were completed successfully and battery
charge was initiated late this afternoon.
1/15/09 - Today the spacecraft
was successfully transported to SLC 2 and mated to the Delta II launch vehicle.
The transport canister has been removed, white room environments
established and post mate operations are continuing by the ULA Team. A small
spacecraft monitor team will remain this evening for inspections during the
mate of the umbilical connections and installation of the level 6 access
platforms. Operations are expected to complete sometime before 2300 hours
PST. On Friday crews will set up equipment and begin mechanical configurations.
1/14/09 - The Transport Can section installations were
completed and the contamination barriers were installed. The spacecraft
was subsequently lifted to the transporter and all purge systems were established. The Launch Site Readiness Review (LSRR) was
conducted at SLC-2W today and all agencies gave the go ahead for spacecraft
mating to the launch vehicle. All systems are go for transport to the
launch pad early AM tomorrow. Weather predictions are for clear skies,
cool temps and light winds.
1/13/09 - The Spacecraft
Transportation Can installation was started today by ULA. The entire can
is now assembled around the spacecraft and final torquing
and wrapping will be performed on Wednesday. Transfer of the spacecraft
to transporter is also planned for Wednesday. The Vandenberg NASA TM
Station, EGSE Crew, and SOCC successfully completed the Stored TIP (STIP) data
dump and data processing from the orbital pass of NOAA-18 over VAFB
today. This test was used to verify the process and configurations for
acquiring first pass data following the launch of NOAA-N Prime.
1/12/09 - Today the crews
installed the Halo/Contamination Barrier onto the spacecraft in preparation for
transport to the launch pad. The second half of the day the crew worked
with ULA to install the Direct Mate Adapter (DMA) onto the Delta PAF and set up
all integrated transportation purges. In parallel all required ground
equipment and flight hardware was packaged and prepared for transport to the
launch pad.
1/9/09-1/11/09 – Pre-transport
inspections and closeouts continued today and are expected to be completed
sometime Saturday. The GRU rack was transported and installed at the
SLC-2 EEB. GRU checkout is ongoing and is expected to be completed late
tonight or on Saturday. Saturday morning will be spent completing any
remaining closeout/inspections and engineering photos. Media photos will
be taken in the afternoon. Sunday is a planned crew rest day.
1/8/09 -
1/7/09 -
1/6/09 -
1/5/09 - Processing resumed
today at VAFB with the remainder of the flight harness mates and battery charge
test setup completed.
1/1/09-1/4/09 –
12/31/08 - The remainder of the
Micro Energy harness testing was completed today with no faults found in the
harness. Following completion of that test, the spacecraft return
to flight configuration and the battery charge test setup was started.
12/30/08 – The
new HI-Pot/Isolation (Micro Energy) test of the mast harness was started today
and is expected to be completed Wednesday morning.
12/29/08 -
Spacecraft processing resumed at VAFB today to continue investigations related
to the Solar Array Diode anomaly. The crew prepared the spacecraft and
measurement equipment for the new HI-Pot/Isolation test of the mast
harness. Testing is expected to begin on Tuesday morning.
12/25/08 – 12/28/08 -
12/21/08 – 12/24/08 - The EGSE Team successfully completed all setup and
checkout activities of the LSE at SLC 2 as planned. Any remaining
checkouts will be completed once spacecraft testing in Bldg. 1610 has
concluded. Planning efforts have
resulted in the approval of a new Hi-Pot/Isolation test on the mast harness
that involves use of a localized Helium environment around the harness.
It is believed that this test is more sensitive and may reveal a shorting path
if one is present. A test team is being assembled to come in during the
holiday break to conduct the test. Actual test activities will be
executed the week of Monday, December 29th and continuing until
testing is complete and the spacecraft is returned to flight configuration.
Current estimates are approximately three days of activities.
12/20/08 - The
decision was made to suspend spacecraft processing at VAFB until additional
harness testing is planned and approved. This planning will take place on
Monday and Tuesday of next week. Spacecraft processing at VAFB will
resume on Monday 12/29. The removed SATCU was opened and inspected in
12/19/08 - The
team successfully removed and SATCU from the spacecraft and replaced it with a
spare unit. The removed unit will undergo bench inspections in
12/18/08 - The
Hi-Pot/Isolation testing of the flight solar array mast harness was
successfully completed today. The Launch Site Equipment (LSE) racks were
shipped out to the launch pad today. The LSE racks and Test Calibration
Unit (TCU) were positioned in the Electrical Equipment Building (EEB), Missile
Service Tower (MST) and Remote Launch Control Center (RLCC). Testing of
this equipment will begin on Friday and is expected to be completed by Tuesday.
12/17/08 - The Hi-Pot/Isolation testing of the ground
support measurement equipment was successfully completed today. All test
equipment is ready for actual measurements of the harness conductors, scheduled
to begin Thursday morning.
12/16/08 - The additional measurements requested as part of
the harness continuity test were completed this morning and yielded nominal
results. Incorporation of the technical and safety comments for the
Hi-Pot /Isolation test was also completed and the document is in the approval
process. Setup is expected to be completed today with hazardous operations
beginning on Wednesday.
12/15/08 - The continuity test was executed successfully
today. Several additional measurements were requested as a result of the
data review. These measurements are planned for tomorrow morning. The technical review of the Hi-Pot/Isolation
test paperwork was completed this evening. Comments from the technical
review will be incorporated on Tuesday. Testing is expected to begin on Tuesday
afternoon or Wednesday.
12/13/08 – 12/14/08 - The review/release of the
harness continuity test paperwork was completed on Saturday morning.
De-mating of the remaining flight connections between the harness and
spacecraft was also completed followed by connection of the ground support
measurement equipment. Sunday was a crew rest day.
12/12/08 - Today was spent preparing paperwork and test
equipment for the Continuity and Hi-Pot/Isolation testing of the Solar Array
Mast Harness. Testing is planned to begin on Saturday afternoon.
12/11/08 -
Inspections of the remaining SEM components were completed successfully (TED
& MEPED). No issues were noted. Spacecraft thermal blanket
inspections are in progress.
12/10/08 - EUMETSAT, Lockheed
Martin and GSFC instrument personnel completed the MHS instrument inspections
on Wednesday. No issues were noted. SEM instrument (TED, MEPED)
inspections are planned for Thursday.
12/9/08 - Northrop Grumman, Lockheed Martin and GSFC
personnel completed the inspections and flight closeouts of the AMSU-A1 and A2
instruments. All inspection data was nominal and no additional cleaning
was required. The flight OSR panel was also installed on the
AMSU-A1. SBUV instrument inspections were also completed today. EUMETSAT
personnel are at VAFB and will perform MHS instrument inspections on Wednesday.
12/8/08 - ITT personnel completed the
inspections and cleaning of the HIRS and AVHRR instruments. All
inspection data was nominal and minimal cleaning was required. The flight
Glint Shield was also installed on the AVHRR. Northrop Grumman personnel
are at VAFB and will perform the AMSU-A1 and A2 inspections and cleaning on
Tuesday.
12/6/08 – 12/7/08 - Clamp band catcher system
buildup continued on Saturday and was completed around noon on Sunday.
Instrument inspections and cleaning are up next starting Monday morning.
Instrument vendors will be at VAFB to support this effort.
12/5/08 - ESA cleaning and clamp band
ordnance installation were completed today. Clamp band catcher system
buildup is in progress and will continue on Saturday. Significant work occurred at the launch pad
this week. The first stage and interstage of our Delta II launch vehicle
were erected at SLC-2 on Tuesday. On Thursday the 3 solid motors
were attached to the first stage. Today the second stage was hoisted into
the tower and mated to the vehicle. Launch vehicle processing continues on
schedule.
12/4/08 - Solar Array snubber
measurements, spacecraft transmitter cooling system flight configuration and
flight antenna standoff installations were completed today. ESA cleaning
will be performed on Friday along with clamp band ordnance installation and
catcher system buildup.
12/3/08 - The solar array mast harness inspections and
testing were completed today. All inspection and test data was
nominal. Planned mechanical work for Thursday includes solar array
snubber measurements, spacecraft transmitter cooling system flight
configuration, flight antenna standoff installation and ESA eyeball cleaning.
12/1/08
– 12/2/08 - NOAA-N Prime vehicle
processing has resumed at VAFB following the Thanksgiving holiday break.
Yesterday afternoon and today have been spent preparing for inspections and
testing on the spacecraft to bring the Solar Array Diode issue to resolution.
Solar Array Harness isolation testing will commence on Wednesday. Following
this testing, mechanical work originally planned for today and the remainder of
the week will continue.
11/24/08
- 11/26/08 -
11/23/08 – The
spacecraft was pressurized with gaseous nitrogen to flight pressure
today. Following pressurization operations, battery discharging
operations commenced and will continue through Wednesday.
11/22/08 – SEPET
test deconfiguration and pressurization preps were completed today. Leak
testing of the reaction control system (RCS) is in progress and will be
completed by Sunday morning. Pressurization to flight pressure will
follow.
11/21/08 – The
Aliveness test, ADCS/SARP3 option retest and UDA/ADA mating/Air link testing
were successfully completed today.
11/20/08 –
Aliveness testing is in progress and should be completed by Friday
morning. Retest of the ADCS/SARP3 downlink checks as well as flight
mating and link testing of the UDA and
11/19/08
– Today the Solar Array Illumination test and Stray
Voltage test were completed. Additional troubleshooting for the
ADCS/SARP3 SEPET Test 6 Option is ongoing and will continue after Aliveness
testing. All SEPET tests are complete with the exception of this option.
Aliveness testing will begin sometime tonight or Thursday morning.
11/18/08 - SEPET testing continued in flow today with no new flags or
anomalies noted. The MHS Instrument testing was successfully completed
and Test 6 Options are continuing.
11/17/08 - SEPET is continuing without
significant issues. Test 6 Options are in work.
Troubleshooting of several procedural problems resulted in slower
than expected progress today however the test is still on track to finish later
this week.
11/16/08 - SEPET is continuing without significant issues. Since yesterday,
Test 4, 5 and several Test 6 options have been completed. Testing is
progressing on schedule.
11/15/08 - SEPET is
continuing with no anomalies noted. TP-ASC and Tests 1, 2 and 3 are
complete. Test 4 is progressing and should be completed within the next
couple of hours. Expect Test 5 to be completed sometime Sunday
morning followed by Test 6 options.
11/14/08 - SEPET is continuing on schedule with no anomalies noted.
11/13/08 - The End to End test between the spacecraft and the SOCC was
successfully completed today. SEPET testing officially began this afternoon and
is expected to continue through the end of next week.
11/12/08 - The first power on cycle of the spacecraft at VAFB
was successfully performed today. Link checks were conducted
on the command and telemetry circuits to verify acceptable data flow for
the upcoming electrical tests. Upon completion of the link checks, the
spacecraft was powered down. End to End testing will commence on Thursday
morning followed by the start of SEPET sometime Thursday evening.
11/11/08 - Today the final configuration activities for the End to End Test
and SEPET were completed. Photo documentation and test set-up inspections
were performed as well. The SEPET TRR was successfully conducted with
several minor actions remaining to be resolved prior to the start of testing on
Thursday evening. The spacecraft will be powered on tomorrow to
verify proper functionality of the command and telemetry
links between the spacecraft and ATNAGE.
11/10/08 - Sunday evening the team completed the battery charging
operation. All cell and pack data collected during the operation was
nominal. Electrical and mechanical preparations for the End to End Test
and SEPET were performed on Monday and are expected to complete on
Tuesday. The End to End Test dry run between the spacecraft
simulator in Lab 3 and the SOCC was successfully performed on Monday as
well. The SEPET TRR is scheduled for Tuesday.
11/09/08 –
11/08/08 - The Building 1610 large doors were opened today to allow removal
of the shipping container, turnover cart and other large shipping
equipment. Following removal of this equipment, the doors were closed and
the highbay was cleaned. The remainder of the day was spent removing the
contamination shroud from the spacecraft and performing all preparations for
battery charge. Sunday the team will execute the battery charge over two
shifts.
11/07/08 - The flight separation system build up continued today. The
clamp band was tensioned to flight levels and will be checked again for proper
tension per procedure on Saturday. The PAF to spacecraft electrical
harnesses were installed, mated and tied down. Installation of the
contamination shroud was completed today in preparation for tomorrow’s
equipment swap.
11/06/08 - The spacecraft was rotated to vertical today and transferred to
the Delta Payload Attach Fitting (PAF). All remaining planned processing
activities through launch will be completed with the spacecraft in the vertical
orientation. Flight separation system (clamp band and catcher) buildup will
continue through tomorrow along with other mechanical and electrical test
preparations. In addition to the work on the spacecraft, the shipping container
cover was reinstalled in preparation for removal from Building 1610, currently
scheduled for Saturday.
11/05/08 - The spacecraft container was opened today and post shipment inspections
were successfully completed. Following inspections, the spacecraft was
removed from the container and transferred to the turnover cart. Rotation to
vertical and transfer of the spacecraft from the turnover cart to the PAF /
milk stool is scheduled for Thursday.
11/04/08 - The NOAA-N Prime Spacecraft was successfully transported to
Vandenberg AFB today, November 4th 2008 and has been secured in the
Building 1610 Hazardous Processing Facility. Processing is set to start
on Wednesday.